The realization f the project titled

„Thermomodernization of the building of the Courageous Crew of ORP “Orzeł” Secondary High School Complex no. 2 in Wejherowo”

In accordance with the Contract no.

Contract no. 567/2014/Wn11/OA-xn-04/D concerning Project 260/2014 from 10 September 2014

on financing the Project has been scheduled as following

Individual stapes of the realization of the Project titled: „Thermomodernization of the building of the Courageous Crew of ORP “Orzeł” Secondary High School Complex no. 2 in Wejherowo” will be executed in accordance with the material-financial schedule which is an integral part of the Contract no. 567/2014/Wn11/OA-xn-04/D concerning the Project 260/2014 from 10 September 2014 on financing the Project. The Project has the following perceived realization stages:

The planned date of commencing the render procedure: November 2014

Project realization stagesRealization commencementRealization conclusion

Thermomodernization of the Courageous Crew of ORP “Orzeł” Secondary High School Complex no. 2 building:

  1. modernization of the installation (central heating, hot utility water) -amount -1 (comprehensive replacement of the central heating installation; replacement of 411 radiators, 411 thermal valves, 4342 liner meters of pipes of DN 15-DN 100 diameter)
  2. thermal insulation of the partitions of the building – surface – 2511,54m2 – (thermal insulation of internal walls on the attic – Styrofoam 15 cm thick, surface 107,85m2; Thermal insulation of the roof of the utilized part of the attic, Styrofoam 25 cm thick, surface 218,6m2; Thermal insulation of the roof over the gym - Styrofoam 25 cm thick, surface 283,77m2; Thermal insulation over the II floor: Styrofoam 25 cm thick, surface 1901,32m2
  3. c. Modernization or replacement of windows – 699,44m2 (modernization or replacement of windows for wooden double glazed ones – 279 units with a thermal coefficient of U=0,9 W/m2K
September – December 2014September – December 2015
PromotionSeptember – December 2014September – December 2015
Supervision inspector (the cost of investment supervision will be covered with the budget funds of the Secondary School Complex no.2 in Wejherowo, separate from the PEP budget)September – December 2014September – December 2015
Financial clearance of the ProjectDecember 2014March 2016

DATA UPDATE

After the tenders, that were a part of this project, have been resolved, some of the funds remained unspent and will be used by the Beneficiary as qualified expenses in accordance with the guidelines concerning qualified expenses that are part of the PL04 Operation Program „Energy conservation and energy sources promotion” as part of the European Economic Area Financing Mechanism 2009-2014”, which were specified in attachment no.4 of the Rules of the Competition to which the application no. 1310/2013 was submitted.

The following table presents the tasks which were completed and the tasks which are qualified expenses – to be realized*

Project realization stagesRealization commencementRealization conclusion
Modernization or replacement of windows for wooden triple glazed ones: 279 units./699,44 m2 with a thermal coefficient of U = 0.9W/m2K11.12.2014 r.01.10.2015 r.
Comprehensive replacement of central heating installation (replacement of 410 radiators, 410 thermal valves, 4430 linear meters of pipes of DN 15- DN 100 diameter)05.05.2015 r.03.12.2015 r.
  1. Thermal insulation of internal walls on the attic: Styrofoam 15 cm thick, surface 107,85 m2
  2. Thermal insulation of the roof of the utilized part of the attic, Styrofoam 25 cm thick, surface 218,60 m2
  3. Thermal insulation of the roof over the gym - mineral wool 25 cm thick, surface 283,77m2
  4. Thermal insulation over the II floor - mineral wool 25 cm thick, surface 1901,32m2
05.05.2015 r.03.12.2015 r.
Thermal insulation of internal basement walls, insulating plates plate 10 cm thick, surface 565,73 m2*04.05.2016 r.August 2016 conclusion of work in accordance with the schedule
Adding external heat insulation of walls in the basement embedded underground. Styrofoam 14 cm thick, surface of 573,172 m2*13.05.2016 r.August 2016 conclusion of work in accordance with the schedule
Replacement of windows in the basement with wooden triple glazed: 10 units/9,6 m2 with heat coefficient of U = 0.9W/m2K*21.03.2016 r.28.04.2016 r.
Renovation of windows in accordance with the renovation works schedule, 15 units/36,59 m2 with heat coefficient of U = 2,6 W/m2K*20.04.2016 r.August 2016 conclusion of work in accordance with the schedule
Renovation of doors in accordance with the renovation works schedule, with heat coefficient of U = 2,6 W/m2K. 8 units/39,105m2*20.04.2016 r.August 2016 conclusion of work in accordance with the schedule
The cost of investment supervision will be covered with the budget funds of the Courageous Crew of ORP “Orzeł” Secondary School Complex no.2 in Wejherowo, separate from the PEP budget December 2014September 2016
Promotion*September 2015September – December 2016

*To be realized

Source: Project Execution Plan (PEP)


Photographic materials from the realization of the Project is available in the Project gallery tab: click here

DATA UPDATE

We hereby inform that on 30.11.2016 an annex no. 2/966 was signed

Concerns:

Extending the range of financing of the project submitted as part of the procedure indicated in Art. 6.9 of the Regulation on introducing the EEA 2009 – 2014 Financing Mechanism – PROGRAM PL04, the Result: Energetic effectiveness.

The following table presents the tasks which were completed and the tasks which are qualified expenses – to be realized*

Project realization stagesRealization commencementRealization conclusion
Modernization or replacement of windows for wooden triple glazed ones: 279 units./699,44 m2 with a thermal coefficient of U = 0.9W/m2K11.12.2014 r.01.10.2015 r
Comprehensive replacement of central heating installation (replacement of 410 radiators, 410 thermal valves, 4430 linear meters of pipes of DN 15- DN 100 diameter)05.05.2015 r.03.12.2015 r.
  1. Thermal insulation of internal walls on the attic: Styrofoam 15 cm thick, surface 107,85 m2
  2. Thermal insulation of the roof of the utilized part of the attic, Styrofoam 25 cm thick, surface 218,60 m2
  3. Thermal insulation of the roof over the gym – mineral wool 25 cm thick, surface 283,77m2
  4. Thermal insulation over the II floor - mineral wool 25 cm
05.05.2015 r.03.12.2015 r.
Thermal insulation of internal basement walls, insulating plates plate 10 cm thick, surface 565,73 m204.05.2016 r.05.09.2016 r.
Adding external heat insulation of walls in the basement embedded underground. Styrofoam 14 cm thick, surface of 573,172 m213.05.2016 r.19.09.2016 r.
Replacement of windows in the basement with wooden triple glazed: 10 units/9,6 m2 with heat coefficient of U = 0.9W/m2K21.03.2016 r.28.04.2016 r.
Renovation of windows in accordance with the renovation works schedule, 15 units/36,59 m2 with heat coefficient of U = 2,6 W/m2K20.04.2016 r.04.10.2016 r.
Renovation of doors in accordance with the renovation works schedule, with heat coefficient of U = 2,6 W/m2K. 8 units/39,105m220.04.2016 r.04.10.2016 r.
Replacement of internal lighting in the school building for an energy efficient variant (LED), in accordance with the project [units/power] -[626/18,03]*January-April 2017 r.January-April 2017 r.
Installation of photovoltaic panels, in accordance with the project [units/kW]–[60/15]*January-April 2017 r.January-April 2017 r.
Replacement of internal lighting in the gym for an energy efficient variant (LED), in accordance with the project [units/power]-[268/7,73]*January-April 2017 r..January-April 2017 r.
Installation of photovoltaic panels with an energy accumulator in the roof of the gym, in accordance with the project [units/kW]–[60/15]*January-April 2017 r.January-April 2017 r.
The cost of investment supervision will be covered with the budget funds of the Courageous Crew of ORP “Orzeł” Secondary School Complex no.2 in Wejherowo, separate from the PEP budget*December 2014 r.April 2017 r.
Promotion*September 2015 rJanuary-April 2017 r.

*To be realized

Source: Project Execution Plan (PEP)


DATA UPDATE IN ACCORDANCE WITH THE PROJECT EXECUTION PLAN – 21.04.2017

The following table present the tasks which were completed as part of this project

Project realization stagesRealization commencementRealization conclusion
Modernization or replacement of windows for wooden triple glazed ones: 279 units./699,44 m2 with a thermal coefficient of U = 0.9W/m2K11.12.2014 r.01.10.2015 r.
Comprehensive replacement of central heating installation (replacement of 410 radiators, 410 thermal valves, 4430 linear meters of pipes of DN 15- DN 100 diameter)05.05.2015 r.03.12.2015 r.
  1. Thermal insulation of internal walls on the attic: Styrofoam 15 cm thick, surface 107,85 m2
  2. Thermal insulation of the roof of the utilized part of the attic, Styrofoam 25 cm thick, surface 218,60 m2
  3. Thermal insulation of the roof over the gym – mineral wool 25 cm thick, surface 283,77m2
  4. Thermal insulation over the II floor - mineral wool 25 cm
05.05.2015 r.03.12.2015 r.
Thermal insulation of internal basement walls, insulating plates plate 10 cm thick, surface 565,73 m2*04.05.2016 r.05.09.2016
Adding external heat insulation of walls in the basement embedded underground. Styrofoam 14 cm thick, surface of 573,172 m2*13.05.2016 r.19.09.2016
Replacement of windows in the basement with wooden triple glazed: 10 units/9,6 m2 with heat coefficient of U = 0.9W/m2K *21.03.2016 r.28.04.2016 r.
Renovation of windows in accordance with the renovation works schedule, 15 units/36,59 m2 with heat coefficient of U = 2,6 W/m2K*20.04.2016 r.04.10.2016
Renovation of doors in accordance with the renovation works schedule, with heat coefficient of U = 2,6 W/m2K. 8 units/39,105m2*20.04.2016 r.04.10.2016
Replacement of internal lighting in the school building for an energy efficient variant (LED), in accordance with the project [units/power]-[690/22,4]03.03.2017 r.30.03.2017
Installation of photovoltaic panels, in accordance with the project [units/kW]–[46/12,88]03.03.2017 r.30.03.2017
Replacement of internal lighting in the gym for an energy efficient variant (LED), in accordance with the project [units/power]-[204/7,1] 03.03.2017 r.30.03.2017
Installation of photovoltaic panels with an energy accumulator in the roof of the gym, in accordance with the project [units/kW]–[74/20,72]03.03.2017 r.30.03.2017
The cost of investment supervision will be covered with the budget funds of the Courageous Crew of ORP “Orzeł” Secondary School Complex no.2 in Wejherowo, separate from the PEP budgetDecember 2014April 2017
PromotionSeptember 2015April 2017
Costs of project management (the additional part)January 2017April 2017

Source: Project Execution Plan (PEP)



Financed from the funds of the EEA 2009 – 2014 Financing Mechanism